are you preparing for the PM exam and want to get ready for the difficult questions in today's video we're
0:06
breaking down 10 of the hardest types of PMP questions you'll learn what makes them challenging strategies to answer
0:13
them effectively and we'll walk through examples for each stick around and by the end of this video you'll feel more
0:20
confident in tackling even the toughest PMP questions let's get started number one
0:27
situational questions situational questions evaluate your ability to apply project management
0:33
principles to real world scenarios these questions typically present a problem or challenge that
0:39
requires you to choose the best course of action based on pmi's guidelines they are designed to test
0:45
your critical thinking problem solving and decision-making skills in Dynamic and often ambiguous
0:51
contexts why it's tough these questions are challenging because they are rarely
0:57
straightforward the scenarios often involve comp in priorities incomplete information and complex Project Dynamics
1:04
you must analyze the situation carefully understand the broader context and prioritize actions that provide the most
1:11
value to the project Additionally the questions often include multiple good sounding options requiring you to
1:18
differentiate between what's good and what's best based on pmi's process-driven approach the ambiguity
1:23
and complexity of these questions can make them difficult to navigate especially under time constraints here are a few tips for
1:30
answering the question when tackling situational questions on the PMP exam
1:36
take a moment to immerse yourself in the scenario think about what's happening Who's involved and what's at stake be
1:42
sure to consider the project context whether you're addressing a risk a stakeholder concern or a deliverable
1:49
issue PMI wants you to think like a project manager who balances competing priorities engages stakeholders
1:56
effectively and makes decisions based on best practices as you review the options think about
2:02
what aligns with pmi's principles typically you'll want to one prioritize
2:08
collaboration and stakeholder engagement over unilateral decision-making two avoid knee-jerk
2:14
reactions that bypass analysis or documentation three focus on proactive
2:20
actions like assessing risks or impacts rather than reactive ones that only solve part of the problem let's look at
2:27
a scenario question together you you are managing a project to develop a new mobile application for a retail company
2:34
during user acceptance testing several critical bugs are discovered that will require at least 2 weeks to fix the
2:40
project sponsor is pressing for the release to stay on schedule citing the high impact of missing the market window
2:46
what is the best course of action a prioritize fixing the critical bugs reschedule the release date and inform
2:53
stakeholders of the delay and the reasons behind it B release the application on time as requested by the
2:58
sponsor and plan A patch update after release to address the critical bugs C conduct a risk analysis of the
3:05
impact of releasing the application with known bugs discuss the risks with the sponsor and key stakeholders and agree
3:11
on the next steps D meet with the development team to assess whether the bugs can be fixed while keeping the
3:17
release on schedule by allocating more resources you can pause the video here if you need more time all right let's
3:25
walk through this together the best answer is C conducting a risk analysis
3:30
is the best approach because it ensures you fully evaluate the implications of releasing the application with critical
3:36
bugs this method allows you to involve key stakeholders in an informed discussion helping you balance the
3:42
Project's priorities risks and stakeholder expectations before deciding on the next steps let's look at other choices and
3:49
why they are wrong option a while rescheduling and fixing the bugs is responsible it bypasses critical
3:56
stakeholder input this Choice also skips the important step of risk analysis which could reveal a more nuanced
4:02
solution option b releasing the app without fully understanding the impact of the bugs could harm the product's
4:08
reputation and user satisfaction this option lacks the necessary risk evaluation and engagement with
4:14
stakeholders option D assessing whether the bugs can be fixed on schedule is a practical step but doing so without
4:21
first conducting a risk analysis may lead to incomplete information and misaligned priorities it's important to
4:27
evaluate the risks first and involve stakeholders into determining the path forward okay let's move on if you are
4:33
ready number two what to do first next questions these questions test your
4:39
ability to sequence project management activities logically and effectively these scenarios require you to determine
4:45
the most appropriate immediate action in a given situation based on the Project's context and pmi's best practices they
4:52
are designed to evaluate your understanding of project process flows problem solving skills and ability to
4:58
prioritize asks why it's tough these questions are
5:04
challenging because they often present several seemingly valid options and distinguishing the best action requires
5:09
a deep understanding of pmi's process-oriented approach it can be difficult to identify what needs to
5:15
happen immediately versus what can wait particularly when faced with competing priorities or overlapping processes
5:22
Additionally the scenarios often introduce multiple layers of complexity such as stakeholder expectations risk
5:29
management and resource constraints requiring you to think holistically and prioritize
5:35
effectively here are a few tips for answering the question to answer these questions effectively first analyze the
5:41
scenario to determine the project phase or process group it pertains to such as initiating planning executing monitoring
5:48
and controlling or closing this helps narrow down the options to actions that align with the
5:53
current stage of the project focus on identifying the primary issue in the scenario and its potential impact on the
5:59
Project's objectives then select the response that resolves the immediate concern while maintaining alignment with
6:05
the overall project plan avoid choosing actions that skip essential steps such
6:11
as analysis or stakeholder engagement even if they seem efficient prioritize proactive measures that address the root
6:17
cause of the issue involve key stakeholders as necessary and ensure project control always aim for responses
6:23
that reflect PMI systematic and logical approach to problem solving let's look at the question together
6:30
you are managing a construction project and during an inspection your team discovers that a key structural
6:36
component has not been installed according to the original design specifications this could cause safety
6:41
issues and result in Project delays what should you do next a immediately halt
6:47
construction and bring the issue to the attention of the project sponsor B conduct an impact analysis to understand
6:54
how this deviation will affect the project schedule budget and safety then determine the necessary corrective
7:01
actions C notify the client about the deviation and the potential safety risks before proceeding with any other actions
7:08
D arrange a meeting with the construction team to determine why the specifications were not followed and
7:14
discussed corrective actions you can pause the video here if you need more time all right let's break this down the
7:22
best answer here is B the first thing you should do is an impact analysis this will help you fully understand the
7:28
Ripple effects of this issue on on your schedule budget and most importantly safety only after you have a clear
7:34
picture should you start discussing Solutions with your team or notifying the client let's look at other choices
7:40
and why they are wrong option a halting construction might be necessary if safety is at risk but you'll want to
7:47
confirm that through the impact analysis first to avoid unnecessary delays option C informing the client too
7:54
early without knowing the full impact or a plan of action could cause unne Neary
7:59
concern you want to have your facts straight before involving them option D meeting with the construction team to
8:06
figure out why this happened is important but you want to do it after you understand the broader impact the
8:12
impact analysis should always come first to guide the next steps okay let's move on if you are
8:17
ready number three stakeholder and communication management questions these questions assess your
8:23
ability to engage stakeholders effectively and ensure clear timely communication throughout the project
8:29
these scenarios test how well you identify stakeholder needs manage expectations and resolve conflicts while
8:35
ensuring project objectives remain on track they also evaluate your understanding of communication
8:40
strategies tailored to different audiences and project contexts why it's tough these questions
8:47
are challenging because they often present conflicting stakeholder priorities or unclear communication
8:53
needs requiring you to interpret the situation carefully the difficulty lies in
8:58
balancing stakeholders satisfaction with project constraints especially when different stakeholders have competing
9:04
demands or a limited understanding of the Project's scope and goals Additionally the scenarios frequently
9:10
involve subtle interpersonal Dynamics or cultural considerations that make choosing the best response less
9:16
straightforward here are a few tips for answering the question to answer these questions effectively start by analyzing
9:23
the stakeholder landscape identify key stakeholders and their levels of influence interest and engagement in the
9:28
project focus on the root cause of the issue presented in the scenario whether it's a lack of information unmet
9:35
expectations or conflicting priorities and consider how your response aligns with pmi's best practices for
9:42
stakeholder in communication management choose actions that promote transparency collaboration and Trust for instance
9:49
engaging stakeholders through tailored communication strategies or involving them in key decisions can often resolve
9:55
tensions and build alignment avoid solutions that ignore stakeholder concerns delay communication or fail to
10:00
address the underlying issue additionally consider the medium and frequency of communication ensuring your
10:06
response Fosters Clarity in alignment by emphasizing clear communication thoughtful engagement and a proactive
10:13
approach to stakeholder needs you can effectively navigate these nuanced scenarios and demonstrate strong
10:18
stakeholder management skills let's look at a stakeholder question together you are managing a
10:25
project with multiple stakeholders including external suppliers and internal teams from different departments a key stakeholder has
10:32
complained that they are not receiving the project updates they need to make decisions in a timely manner you reviewed your communication management
10:38
plan and found that their updates have been sent regularly what is the best approach to resolve this issue a send
10:45
the stakeholders more detailed project updates and increase the frequency of communication to ensure they feel more
10:51
informed B meet with the stakeholder to discuss their specific communication needs and adjust the communication
10:57
management plan to better suit their preferen C reconfirm the communication management
11:02
plan with all stakeholders and clarify the schedule and content of updates to avoid future
11:08
misunderstandings D conduct a survey of all stakeholders to assess the effectiveness of current Communications
11:14
and identify areas for improvement before you pause the video if you are enjoying this content and find it
11:20
helpful please like this video and consider subscribing to our Channel your support goes a long way all right let's
11:27
think through this one the best answer is B the first thing you want to do is
11:32
sit down with the stakeholder and have a conversation by asking them directly about their specific communication needs
11:37
you'll get a better understanding of what's missing from their perspective then you can tweak your communication
11:43
plan to keep them in the loop in a way that works for them let's look at other choices and why they are wrong option A
11:50
sending more detailed and frequent updates might help but it could overwhelm the stakeholders if that's not
11:56
the root of the problem always best to ask what they want first option C
12:01
reconfirming the communication plan with all stakeholders can help clarify expectations but it's not as personal or
12:07
specific as meeting with the individual who has the concern it's a good General approach but might not fully resolve the
12:14
issue for that particular stakeholder option D a stakeholder survey could provide some insights but
12:20
it's a broad approach right now you're dealing with a specific complaint from one stakeholder so focusing on that
12:26
conversation first is a better use of time okay let's move on if you are ready
12:32
number four riskmanagement questions these questions evaluate your
12:37
ability to identify analyze and respond to risks throughout the Project Life Cycle the questions test your knowledge
12:43
of proactive risk management practices including assessing risk probability and impact developing response strategies
12:49
and integrating risk management into the broader project plan you may need to address existing risks emerging risks or
12:56
overall risk planning in Dynamic project scenarios why it's tough these questions are
13:02
challenging because they require you to analyze complex risk scenarios prioritize effectively and apply the
13:09
appropriate response strategies you must think proactively balancing the Project's objectives constraints and
13:15
stakeholder expectations scenarios often involve multiple risks or shifting project conditions requiring strategic
13:22
thinking and a deep understanding of pmi's riskmanagement processes here are a few tips for
13:28
answering the question to answer effectively identify the key risks in the scenario and assess their
13:34
probability impact and urgency focus on solutions that address the root cause of the risk while aligning with project
13:40
objectives and stakeholder needs choose responses that demonstrate proactive systematic risk management such as
13:47
updating the risk register implementing a predefined response or communicating adjustments to the plan avoid reactive
13:54
fixes or decisions that ignore long-term implications let's look at a risk management question question together
14:00
during a large construction project a major supplier notifies you that they may not be able to deliver materials on
14:06
time due to unforeseen production issues this risk was identified in your risk register and classified as a high
14:12
probability high impact risk you already have a contingency plan in place for this risk what should you do next a
14:20
activate the contingency plan immediately and notify stakeholders about the potential delay B monitor the
14:26
supplier situation closely and wait to see if the materials can be delivered on time before activating the contingency
14:33
plan C review the contingency plan to ensure it still aligns with the current project situation and determine if
14:39
adjustments are needed D escalate the issue to the project sponsor to ensure that they are aware of the supplier's
14:46
challenges and seek their advice you can pause the video here if you need more time all right let's walk through this
14:54
the best answer is a since you've already planned for this exact situation the best thing to do is activate your
14:59
contingency plan right away you don't want to wait around and risk further delays once you've set the plan in
15:06
motion you can inform your stakeholders about the potential delay and what steps you're taking to handle it this keeps
15:12
things moving smoothly let's look at other choices and why they are not the best answer option
15:18
b monitoring the situation might feel like a cautious approach but if you wait too long you could end up causing more
15:23
delays it's better to be proactive and start implementing the solution option C reviewing the
15:30
contingency plan isn't a bad idea but since you already developed the plan specifically for this high impact risk
15:37
it's better to act quickly you can always fine-tune the plan if necessary but don't let that slow down your
15:43
response option D escalating to the project sponsor should be reserved for situations where you don't have a plan
15:49
in place or when things are beyond your control here you've already prepared for this risk so there's no need to escalate
15:55
right away okay let's move on to the next one if you are ready number five
16:00
change management questions these questions assess your ability to handle changes to the project
16:05
scope schedule cost or other baselines in a structured and controlled manner these scenarios test your understanding
16:11
of PMI Change Control process including evaluating change requests analyzing
16:17
their impact engaging stakeholders and updating the project plan and documentation
16:22
accordingly why it's tough change management questions are challenging because they require you to apply both
16:29
strategic and procedural thinking you must evaluate the potential impact of a change across multiple project areas
16:35
such as scope schedule cost and risk while navigating competing stakeholder priorities the scenarios often involve
16:42
balancing the urgency of a requested change with a need for thorough analysis and adherence to formal change control
16:48
processes additionally these questions test your ability to make decisions that align with PMI best practices even when
16:55
faced with pressure to act quickly here are a few tips for answering the question to answer these questions
17:02
effectively first evaluate the nature and scope of the proposed change identify its potential impacts on the
17:08
Project's baselines and assess whether it aligns with the Project's objectives and constraints always consider the role
17:14
of the Change Control Board or other governance bodies in reviewing and approving significant changes focus on responses that
17:21
demonstrate a structured approach such as conducting an impact analysis engaging stakeholders and documenting
17:27
changes in the project management plan avoid skipping key steps in the process
17:32
such as analyzing impacts or seeking stakeholder input even if a quicker resolution seems appealing additionally
17:39
prioritize solutions that maintain transparency and Foster stakeholder alignment let's look at a change
17:44
management question together you are managing a project to upgrade the it infrastructure for a multinational
17:51
company a key stakeholder has requested a change to include additional security features not originally in scope the
17:57
impact analysis has been complet completed showing that the change will require additional funding and extend
18:02
the timeline by 2 weeks the Change Control Board is scheduled to meet in 3 days however the stakeholder is pressing
18:10
for an immediate decision citing the urgency of potential security vulnerabilities what should you do next
18:17
a approve the change on your own to address the security risks immediately and notify the Change Control Board at
18:24
their scheduled meeting B inform the stakeholder that the decision will be made during the Change Control board
18:30
meeting and ensure they understand the importance of adhering to the formal process C escalate the stakeholders
18:38
concerns to the project sponsor to gain immediate approval for the change ahead of the Change Control board meeting DW
18:45
work with the stakeholder to identify interm measures to mitigate the security risks until the Change Control Board
18:51
reviews and decides on the change request you can pause the video here if you need more time all right let's break
18:58
this down the best answer is D the best course of action is to work with the
19:04
stakeholders to identify interim measures to address the security risks until the Change Control board meeting
19:10
this ensures that urgent concerns are addressed without bypassing the formal change management process maintaining
19:15
project governance and stakeholder trust let's look at other choices and why they are not the best answer option A
19:23
approving the change independently undermines the authority of the Change Control Board and bypasses the EST
19:28
established process which could lead to governance issues and set a bad precedent for handling future
19:34
changes option b while waiting for the Change Control board meeting adheres to the formal process it ignores the
19:40
urgency of the security risks failing to address the stakeholders concerns promptly could damage relationships and
19:47
potentially expose the project to vulnerabilities option C escalating the issue to the sponsor for immediate
19:54
approval bypasses the Change Control Board and may create unnecessary tension among stakeholders especially if the
20:00
sponsor's decision conflicts with the Change Control board's eventual review okay let's move on to the next
20:06
one if you are ready number six leadership style and Team Management
20:11
questions these questions are designed to test how effectively you can guide and support a team to achieve project
20:17
objectives these questions often involve scenarios where you need to address Team Dynamics resolve conflicts motivate
20:24
individuals or choose the right leadership style for a given situation the focuses on how you manage
20:30
interpersonal challenges while keeping the project on track why it's tough
20:35
these questions can be tricky because they deal with ambiguity there's rarely one right answer you'll need to analyze
20:41
the scenario identify the key issues and select an approach that balances competing priorities like addressing
20:47
team morale while meeting tight deadlines leadership requires adaptability so you'll need to consider
20:53
factors like team maturity urgency and individual personalities additionally
20:58
these questions test your emotional intelligence your ability to recognize and address Team Dynamics while
21:04
maintaining trust and Alignment here are a few tips for answering the question
21:09
take a moment to fully understand the scenario and pinpoint the team's immediate needs ask yourself does the
21:14
team require clear Direction collaboration or individual support once you've identified the problem align your
21:20
approach with the appropriate leadership style choose answers that balance team needs with project goals PMI favors
21:28
Solutions that address challenges constructively maintain trust and keep the project on track avoid rigid or
21:34
punitive actions and prioritize open communication the best responses often involve engaging the team seeking input
21:41
and maintaining a positive environment while focusing on long-term success let's look at a team management
21:47
question together you are leading a diverse project team that has experienced recent conflicts over task
21:53
assignments some team members feel that they are being given too much responsibility While others are diss
21:58
satisfied with the lack of challenging tasks morale is starting to drop as a
22:03
project manager how should you address this situation A use a Democratic Leadership
22:09
style and hate hold a team meeting to allow members to voice their concerns and collectively decide on how tasks
22:15
should be assigned B apply a coaching leadership style meet with each team member individually to understand their
22:21
preferences and strengths and reassign tasks accordingly C take an authoritative
22:28
leadership approach and reassign tasks based on your assessment of each team member's skills and the Project's needs
22:35
de Implement a Lay's Fair leadership style to allow the team to self-organize and redistribute tasks among themselves
22:42
you can pause the video here if you need more time all right let's break this down the best answer is b a coaching
22:49
leadership style is the way to go here by meeting with each team member one-on-one you can get a deeper
22:56
understanding of their strengths preferences and frustrations this lets you reassign tasks in a way that plays to their
23:02
individual strengths and keeps everyone motivated it's a thoughtful personalized approach that Fosters trust in morale
23:10
let's look at other choices and why they are not the best answer option a holding a team meeting and letting everyone have
23:16
their say is helpful but it might not get to the root of the issue a democratic approach can open up dialogue
23:22
but it may not fully resolve the underlying concerns especially if individual strengths and weaknesses
23:28
aren't addressed option C being authoritative in reassigning tasks on your own could
23:33
solve the immediate issue but it risks lowering morale even further if the team feels like their concerns aren't being
23:39
heard it's a more top-down approach which might not work well in this situation option D L says Fair
23:46
leadership where you let the team sort it out themselves could lead to even more conflict and confusion it's better
23:52
to step in and provide guidance rather than leaving the team defend for themselves okay let's move on if if you
23:58
are ready number seven hybrid and agile project management questions these questions assess your
24:05
understanding of agile principles practices and their integration with traditional project management Frameworks the questions often test your
24:12
ability to manage Dynamic environments where itera approaches like scrum or can ban coexist with predictive waterfall
24:20
processes you'll encounter scenarios that require balancing flexibility stakeholder collaboration and value
24:27
delivery while adhering to project constraints like budgets schedules or regulatory
24:32
requirements why it's tough these questions are challenging because they require a deep understanding of both
24:39
agile and predictive methodologies and the ability to integrate them seamlessly scenarios often involve competing
24:46
priorities such as maintaining a fixed timeline while incorporating iterative feedback you must balance the need for
24:52
flexibility with adherence to project constraints all while keeping stakeholders aligned the added complex
24:58
of Hybrid models means you need to think critically about how agile and predictive elements interact and influence one another here are a few
25:06
tips for answering the question when answering these questions start by identifying the key challenge
25:12
in the scenario whether it's a scheduling conflict a stakeholder concern or balancing iterative delivery
25:18
with predictive requirements focus on responses that align with agile principles like delivering value early
25:25
and involving stakeholders while respecting fixed constru straints from the predictive side avoid solutions that
25:31
overly favor one methodology at the expense of the other as hybrid approaches require thoughtful
25:37
integration choose actions that demonstrate collaboration proactive communication and adaptability for
25:43
example responses that involve engaging stakeholders refining processes or prioritizing value delivery while
25:50
maintaining alignment with constraints are typically best avoid rigid responses that dismiss either agile's flexibility
25:56
or the control of predictive methods a balanced systemwide approach that reflects the benefits of both
26:01
methodologies will help you excel in these scenarios let's look at a hybrid agile question together you are managing a
26:09
hybrid project that uses agile for development and a predictive approach for deployment mids Sprint a stakeholder
26:15
urgently requests a new feature emphasizing its importance for meeting Market demands the project sponsor has
26:21
emphasized that the timeline cannot be extended due to contractual obligations the development team is concerned that
26:27
the change will disrup up their Sprint goals how should you proceed a add the
26:32
feature to the Sprint backlog and work with the development team to rep prioritized tasks ensuring the most
26:38
critical deliverables are completed on time B defer the requested feature to the next Sprint informing the
26:45
stakeholder that changes cannot be introduced mid-print and offering to address their concerns during Sprint
26:51
planning see facilitated discussion between the stakeholder the development team and the sponsor to assess what
26:58
whether the feature can be handled as a separate expedite deliverable outside the current Sprint D approve the feature
27:05
request and instruct the development team to adjust their Sprint goals to accommodate the change ensuring the
27:11
timeline is not impacted you can pause the video here if you need more time all
27:17
right let's walk through this the best answer is C facilitating a discussion between the stakeholder development team
27:23
and sponsor is the best approach this collaborative effort allows for exploring whether the feature can be
27:29
handled separately from the current Sprint minimizing disruption while addressing stakeholder urgency it
27:35
balances the agile principle of respecting the Sprint backlog with the need for flexibility in hybrid
27:41
projects let's look at other choices and why they are not the best answer option
27:46
a while reprioritizing tasks to accommodate the change might seem proactive it disrupts agile practices of
27:52
maintaining a stable Sprint backlog this approach risks overloading the team and compromising Sprint goals without
27:58
stakeholder consensus option b deferring the feature aligns with agile principles but may not
28:04
address the stakeholders urgency or demonstrate responsiveness to their concerns potentially damaging trust and
28:11
collaboration option D approving the request and forcing the team to adjust mid-print undermines agile processes and
28:18
risks quality issues or burnout it also fails to consider the broader project context such as stakeholder alignment
28:25
and sponsor constraints okay let's move on of you are ready number
28:30
eight earned value management questions earned value management evm
28:36
questions assess your ability to analyze and interpret project performance data using evm
28:42
metrics these metrics include planned value earned value actual cost and derived indicators like cost performance
28:49
index schedule performance index cost variance and schedule variance these questions test your
28:55
ability to evaluate whether a project is on track back regarding budget and schedule and make datadriven decisions
29:01
to address Performance issues why it's tough earned value management evm
29:08
questions are difficult because they require both precise calculations and the ability to interpret results
29:15
effectively the formulas involved can be intimidating and questions often combine multiple steps requiring you to
29:21
calculate several metrics before arriving at the correct answer additionally understanding what the
29:27
metrics imply about project performance and deciding on the best course of action adds a layer of complexity in an
29:33
exam setting the time pressure to solve problems quickly and accurately further increases the challenge here are a few tips for
29:40
answering the question to succeed with evm questions it's essential to memorize the key
29:46
formulas and understand what each metric indicates about the Project's health for instance knowing that a CPI
29:54
above one means the project is under budget while an SPI below one indicates it is behind schedule allows you to
30:01
interpret results effectively take time to read the question carefully identifying whether
30:07
it focuses on budget schedule or overall project performance work systematically
30:12
through multi-step problems ensuring accuracy at each stage of the calculation beyond the math think
30:19
critically about what the metrics mean and what corrective actions are appropriate as evm questions often test
30:25
decision-making skills as much as technical knowledge by combining a strong grasp of formulas
30:30
with strategic interpretation you can confidently tackle these challenging questions let's look at an earned value
30:37
management question together you are managing a project with a total budget of
30:43
$800,000 at this point 50% of the project work is completed and the team
30:48
has spent $450,000 however the planned work should have been 60% completed by now what are
30:55
the cost performance index CPI and schedule performance index SPI and what
31:01
do they indicate acpi 0.89 SPI
31:06
0.83 the project is over budget and behind schedule B CPI 1.11 SPI 0.83 the project
31:16
is under budget but behind schedule CPI 0.89 SPI 0.92 the project
31:23
is over budget but slightly behind schedule DCP Pi 1.11 SPI 1.0 the project
31:31
is under budget and on schedule you can pause the video here if you need more time all right let's break this down
31:38
step by step the best answer is a to calculate the CPI cost performance index
31:45
you divide earned value EV by actual cost AC in this case the EV is 50% of
31:51
$800,000 which is $400,000 the team has spent $450,000
31:58
so CPI $400,000 divided by $450,000 equals
32:04
0.89 meaning the project is over budget now for the SPI schedule performance
32:10
index you divide EV by Planet value PV PV should be 60% of
32:15
$800,000 which is $480,000 so SPI is equal to
32:21
$400,000 divided by $480,000 and that gives us 0.83 meaning the project is behind
32:29
schedule let's look at other choices option b got the SPI correct but
32:34
the CPI is off this project isn't under budget it's over option C the
32:40
calculation for CPI is correct but the SPI is slightly off you've got the right
32:45
idea this project is over budget and behind schedule but the SPI should be a bit
32:51
lower option D is incorrect the calculations for both CPI and SPI are
32:56
wrong here lead leading to the wrong conclusion that the project is on schedule and under budget which isn't
33:02
the case okay let's move on if you are ready number nine PMI code of ethics and
33:09
professional conduct PMI code of ethics and professional conduct questions assess
33:14
your understanding of ethical decision-making and professional responsibilities as a project manager
33:19
these questions focus on the core values outlined in pmi's Code of Ethics responsibility respect fairness and
33:25
honesty you'll encounter scenarios where you need to navigate ethical dilemmas handle conflicts of interest ensure
33:32
fairness or protect confidentiality the goal is to evaluate how well you uphold
33:37
pmi's ethical standards while balancing project and stakeholder demands why it's tough ethics questions
33:45
are challenging because they often present scenarios with competing priorities requiring you to navigate
33:50
ambiguity and balance ethical Integrity with professional responsibilities these questions test
33:55
your ability to align your decisions with pmi's core values responsibility respect fairness and honesty while
34:02
addressing stakeholder demands organizational constraints and sometimes emotionally charged situations the
34:08
correct answer often requires careful analysis and prioritizing long-term trust over short-term
34:14
convenience here are a few tips for answering the question to succeed start
34:19
by identifying the ethical principles being tested such as fairness or transparency focus on responses that
34:25
demonstrate Integrity accountability and respect for for all stakeholders avoid options that suggest
34:31
dishonesty bias or neglecting ethical duties choose actions that promote open communication build trust and align with
34:38
pmi's core values even if they involve difficult conversations or Decisions by
34:43
prioritizing professionalism and long-term relationships you can confidently navigate these
34:48
scenarios let's look at a code of ethics question together you are the project manager for a large government project
34:56
during a team meeting a colleague suggests using a subcontractor they know but fails to disclose their personal
35:02
relationship with the subcontractor's owner you suspect a potential conflict of interest what is the best course of
35:08
action a report the potential conflict of interest to your legal department to ensure transparency and compliance with
35:14
government policies B privately speak with your colleague reminding them to disclose any
35:20
personal relationships that could affect decision-making and Report the conflict if necessary C exclude the subcontractor
35:29
from consideration entirely to avoid any appearance of impiety and maintain project Integrity D allow the
35:37
subcontractor to participate in the bidding process but ensure there is a competitive and transparent selection
35:42
process to prevent favortism you can pause the video here if you need more time all right let's unpack this one the
35:50
best answer is B the best course of action is to First have a private conversation with your colleague this
35:56
approach allows them the opportunity to disclose the relationship voluntarily maintaining trust and professionalism if
36:02
the conflict is not disclosed or addressed after the conversation escalation may be necessary but giving
36:08
them a chance to correct the situation is the most balanced and ethical First Step let's look at other choices and why
36:15
they are not the best answer option a reporting the conflict immediately to the legal department ensures compliance
36:21
but is too drastic as an initial step directly involving legal could harm trust and Team Dynamics without first
36:28
understanding the full context or giving your colleague a chance to address the issue themselves option C excluding the
36:36
subcontractor out rate may seem like a clean solution but it is premature and unfair without confirming whether the
36:42
relationship creates a genuine conflict of interest this approach also risks alienating the colleague and overlooking
36:48
a potentially qualified subcontractor option D allowing the subcontractor to bid while ensuring
36:55
transparency is a reasonable approach but it assumes the conflict of interest has already been disclosed and addressed
37:02
moving forward without first addressing the ethical concern could undermine fairness and Trust okay let's move on if you are
37:09
ready number 10 integrated project management questions these questions evaluate your
37:16
ability to coordinate all aspects of a project such as scope cost schedule risk
37:21
and resources into a cohesive plan the questions focus on how well you manage interdependencies and balance competing
37:27
priorities to achieve project objectives scenarios often involve unexpected changes or conflicts requiring you to
37:34
assess the Ripple effects of decisions across multiple project areas why it's tough these questions are
37:41
challenging because they require a broad understanding of how different project components interact you need to evaluate
37:47
the impact of changes in one area on the rest of the project often with limited information the difficulty lies in
37:54
balancing trade-offs between competing priorities making form decisions under uncertainty and thinking holistically to
38:01
avoid unintended consequences here are a few tips for answering the question to answer these
38:07
questions effectively focus on identifying the core issue and how it affects the Project's interdependent
38:13
elements consider the broader implications of changes in scope cost or schedule and choose options that balance
38:19
priorities while maintaining alignment with project goals avoid responses that focus
38:24
narrowly on a single problem without addressing the broader imp prioritize actions that involve revisiting the project plan
38:31
collaborating with stakeholders and using structured processes like change control or risk management the best
38:37
answers demonstrate a thoughtful systemwide approach that keeps the project aligned with organizational
38:43
objectives let's look at an integrated project management question together you are managing a project to launch a new
38:50
e-commerce platform during a progress review you discover that a key module does not meet functional requirements
38:56
due to a design oversight fixing this issue will require significant rework increasing costs by 15% and delaying the
39:04
timeline by 3 weeks the sponsor is insistent on meeting the original deadline due to a high-profile marketing
39:10
campaign already scheduled what is the best course of action a propose a
39:16
temporary workaround for the module to meet the functional requirements at a basic level ensuring the platform
39:21
Launches on schedule and plan to address the oversight in future updates B conduct an impact analysis of
39:28
delaying the fix until after the platform's launch and present options to stakeholders emphasizing the importance
39:34
of meeting the original deadline C facilitate a meeting with key stakeholders including the sponsor to
39:41
discuss the trade-offs between quality cost and timeline and collaboratively decide on the path forward de adjust the
39:49
platform scope to exclude the problematic module focusing on delivering a highquality product for the
39:54
remaining features while communicating the adjustment to stakeholders post launch you can pause the video here if
40:00
you need more time all right let's break this one down the best answer is C
40:06
because it ensures transparency collaboration and Alignment among all stakeholders this approach allows for
40:11
informed decision- making based on a holistic view of project priorities and constraints let's take a look at other
40:18
choices option A is an appealing choice because proposing a temporary workaround might seem to balance functionality and
40:24
timeline but it risks compromising quality quality and user experience leading to long-term reputational
40:31
damage option b focuses on maintaining the timeline and encourages analysis but
40:37
delaying the fix without full stakeholder engagement could lead to unresolved quality issues and
40:42
stakeholder dissatisfaction option D is tempting because narrowing the scope could ensure
40:47
a highquality launch for other features but it sidesteps the critical need for stakeholder input and risks misalignment
40:54
with project objectives there you go the 10 hardest types of PM questions we covered a lot
41:01
in this video and you may want to rewatch it to let these Concepts sync in you can use the timestamp to jump to any
41:08
type of question you want to review before we wrap up here is a thank you bonus for completing the 10
41:14
questions with final tips to help you tackle any challenging PMP
41:19
questions one take your time when you come across a tough question don't rush
41:25
through it take a moment to fully understand what's being asked often the key to the right answer is hidden in the
41:32
details and rushing can make you miss important Clues two eliminate the obvious wrong
41:39
answers sometimes the trick is not in finding the right answer right away but eliminating the obviously wrong ones
41:45
narrow down your options using the strikeout feature so you can focus on the best possible choice three think
41:52
like PMI not just like a project manager remember the PMP exam tests you
41:58
on pmi's best practices not necessarily what you would do in your own projects
42:03
always consider the pmi's preferred approaches when making your choice four trust your knowledge don't
42:11
overthink it's easy to second guess yourself especially on tricky questions but often your first instinct is correct
42:17
if you've studied well trust in your preparation and avoid over complicating the question five practice practice
42:25
practice find nothing beats practice the more PMP exam style questions you tackle
42:32
the more familiar you'll become with the patterns and logic of these questions so make practice exams your best friend I
42:39
hope you find this video helpful as it takes many hours to put it together if so please like the video and consider
42:46
subscribing to PM aspirant for more PMP exam tips and strategies so how many did you answer
42:52
correctly do you want more PMP exam prep videos like this one please let me know in the comments below if you want more
43:00
practice questions please check out the link in the video description thank you for watching till the end of this video
43:06
and I wish you the best of luck with your PMP exam lastly if you have not done so make sure you also watch the PMP