Last Updated on November 27, 2021 by andrewshih
PMP Formulas Cheat Sheet
The PMP cheat sheet is aligned with PMP PMBOK 6 and includes the PMP exam formulas that you will need to know to pass the PMP exam.
Cost Management Formulas
PV | Planned Value |
EV | Earned Value |
AC | Actual Cost |
BAC | Budget at Completion |
EAC | Estimate at Completion |
Use the chart to help you understand the cost management formulas.
Cost Variance: CV = EV – AC | |
The amount of budget deficit or surplus | + = Under planned cost 0 = On planned cost – = Over plan cost |
Schedule Variance: SV = EV – PV | |
The amount by which the project is ahead or behind the planned delivery date. | + = Ahead of Schedule 0 = On Schedule – = Behind Schedule |
Variance at Completion: VAC = BAC – EAC | |
A projection of the amount of budget deficit or surplus. | + = Under Planned Cost 0 = On Planned Cost – = Over Planned Cost |
Cost Performance Index: CPI = EV / AC | |
Shows the percentage of how much costs are over or under the amount of work accomplished. | Greater than 1.0 = Under planned cost 1.0 = On planned cost Less than 1.0 = Over planned cost |
Schedule Performance Index: SPI = EV / PV | |
A measure of schedule efficiency. | Greater than 1.0 = Ahead of Schedule 1.0 = On Schedule Less than 1.0 = Behind Schedule |
Estimate at Completion: The expected total cost of completing all work expressed as the sum of the actual cost to date and estimate to complete. | |
EAC = AC + ETC | If the initial plan is no longer valid. Use new estimate. |
EAC = AC+BAC-EV | If the future work will be accomplished at the planned rate, use the remaining budget. |
EAC = BAC/CPI | If CPI is expected to be the same for the remainder of the project. |
EAC = AC+(BAC-EV)/(CPI*SPI) | If both CPI and SPI influence the remaining work. |
Estimate to Complete: The expected cost to finish all remaining project work. | |
ETC = EAC – AC | Assuming the work is proceeding on plan |
To Complete Performance Index: A measure of the cost performance that must be achieved with the remaining resource in order to meet a specific management goal. | |
TCPI = remaining work/budget available | Greater than 1.0 = Harder to complete 1.0 = Same to complete Less than 1.0 = Easier to complete |
TCPI = (BAC-EV)/(BAC-AC) | The efficiency that must be maintained in order to complete on plan |
TCPI = (BAC-EV)/(EAC-AC) | The efficiency that must be maintained in order to complete the current EAC. |
Schedule Management Formulas
PERT Weighted Average = (O+4M+P)/6 |
PERT Standard Deviation = (P-O)/6 |
Project Evaluation & Review Technique for estimating activity duration. O=optimistic, M=Most likely, P=Pessimistic |
Float (or slack) = LS – ES Float (or slack) = LF – EF | LS = Late Start ES = Early Start LF = Late Finish EF = Early Finish |
Communication Management Formulas
Communication Channels = N(N-1)/2 |
Need more than just a PMP formulas cheat sheet?
If you are looking for a more cmoprehensive preparation of all the formula questions that may appear on the PMP exam, PM-Prepcast formula package will be your best bet.
PM-Prepcast Formula Package $29.00
- Comprehensive PMP Formula study guide
- Formula Pocket Guide (Brain Dump)
- 105 formula sample questions with detail answers (PDF)
- Formula Keywords Review
- 16 Daily emails with formula tips and tricks
- and much more…
Additional PM Exam Resource
In additional to this PMP Formulas Cheat Sheet, you may want to check out the resource page for recommended resource and links to a collection of free exam questions. If you are looking for a study guide, check out the PMP Study Guide with Pros/Cons of most popular PMP books including Rita Mulcahy, Andy Crowe, and Head First PMP.